PROJECT NAME: Driftwood LNG Phase 1 OWNER: Driftwood LNG LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: 10 November 2017 | CHANGE ORDER NUMBER: CO-002 DATE OF CHANGE ORDER: July 24, 2019 |
I. | Scope Adjustments |
1. | Contractor shall be responsible for installation of a tie-in and meter for municipal water required for construction and pay for same. Contractor assumes that this tie-in will have the capacity to supply approximately 250 gpm at 52 psig. Contractor shall provide and distribute water for Phase 1 construction activities on the Site until Substantial Completion of Project 2. |
2. | Owner shall be responsible for installation of a tie-in and meter for municipal water required for potable uses for the Liquefaction Facility and pay for same. This tie-in will have the capacity to supply approximately 100 gpm at 52 psig. |
3. | Owner shall be responsible for installation of a tie-in and meter for municipal water required for firewater use for the Liquefaction Facility and pay for same. This tie-in will have the capacity to supply approximately 500 gpm at 52 psig for a period of 8 hours. |
1. | Connection number 1: Owner shall be responsible for installation of a 6” header 150# tie-in north of building parking lot area for municipal water, as depicted on Exhibit C of Driftwood LNG Phase 1 Change Order number CO-002, required for potable uses for the Liquefaction Facility and pay for same. This tie-in will have the capacity to supply 100 gpm at a minimum pressure of 50 psig. A meter will be installed adjacent to the public portion of Burton Shipyard Road. |
2. | Connection number 2: Owner shall be responsible for installation of a 12” header 150# tie-in for well water required for fire/Demin/utility water use, as depicted on Exhibit C of Driftwood LNG Phase 1 Change Order number CO-002, for the Liquefaction Facility and pay for same. This tie-in will have the capacity to supply 1375 gpm at a minimum pressure of 50 psig. |
3. | Connection number 3: Owner shall be responsible for installation 2” header 150# potable water connection (from 6” header referenced in connection number 1) for Main Guard House. The tie in point will be just south of Main Guard House as depicted on Exhibit C of Driftwood LNG Phase 1 Change Order number CO-002. This tie-in will have the capacity to supply at a minimum pressure of 50 psig. |
4. | Connection number 4: Contractor shall be responsible for installation of a tie-in and meter for municipal water required for construction water and pay for same. Contractor will use the existing 6” header along Burton Shipyard Road and this tie-in will have the capacity to supply a minimum 250 gpm at a minimum pressure of 50 psig. Contractor shall use this connection to provide and distribute water for construction activities on the Site through all Phases of construction. Owner will not demolish or remove this 6” line prior to completion of all Phases of construction. |
5. | Connection number 5: Contractor shall be responsible for installation of a tie-in and meter for municipal water required for construction water and pay for same. Contractor will use the existing 10” header along Global Drive and this tie-in will have the capacity to supply a minimum of 250 gpm at a minimum pressure of 50 psig. Contractor shall use this connection to provide and distribute water for construction activities on the Site through all Phases of construction. Owner will not demolish or remove this 10” line prior to completion of all Phases of construction. |
6. | Contractor Owner will supply and install three water wells (up to 500 feet deep each and spaced 100 feet apart) on the Site off-site to supplement and/or substitute for water provided by the municipal water system to meet water requirements as described above. The water wells will be designed with 500 gpm pumping capacity per well. The pumping capacity, spacing and depth of the wells are subject to change based on field verification (test wells). Owner will provide water (quantity, quality, and delivery conditions) as specified in Exhibit C of Driftwood LNG Phase 1 Change Order number CO-002. Contractor shall be entitled to a Change Order should field verification warrant modifications to the existing design in order to meet the required flowrates and quality for the firewater and utility/process water systems. Contractor assumes that the water quality from the wells on Site is consistent with the Calcasieu Parish water quality data in the Chicot Aquifer Summary Baseline Monitoring Report, FY 2002, Louisiana Department of environmental Quality. Owner will allow Contractor to use excess well water, assuming wells are first used to supply all appropriate Liquefaction Facility operation uses, for construction purposes for all Projects.” |
Description of Data/Information/Documents Provided | Date Provided or to be Provided | |
1.7 | Owner to provide written confirmation to Contractor that utility companies have disconnected all existing customers served by water, sewer, power, and telecommunication utilities crossing or within the Site boundaries and that above mentioned utilities are no longer required. | 30 days prior to NTP |
Description of Data/Information/Documents Provided | Date Provided or to be Provided | |
2.8 | Provide municipal water supply to the designated tie-in points in accordance with Attachment 25, Exhibit 25-1 and Attachment 1, Schedule 1-1, Section 5.15.2 as agreed and modified in Driftwood LNG Phase 1 Change Order number CO-002. | At NTP Connection number 1: 6” header 150# potable water: connection and water supply provided prior to month 7 after NTP. Connection number 2: 12” header 150# tie-in and meter for well water required for fire/Demin/utility water use connection provided prior to month 7 after NTP and water supply available prior to 20 months after NTP Connection number 3: 2” header 150# potable water: connection and water supply provided prior to month 7 after NTP. |
Description of Data/Information/Documents Provided | Date Provided or to be Provided | |
2.15 | a) Provide expansion of (i) Burton Shipyard Road including all associated utilities, easements, etc. so as to provide access to the Site according to the indicative standard in Exhibit 21-1. Owner is responsible for the construction of the road improvements Burton Shipyard Road from Highway 27 to approximately 3040 feet east of Global Drive intersection and (ii) Highway 27 including all associated utilities, easements, etc. so as to provide access to the Site according to the indicative standard in Exhibit 21-2. 180 Days after NTP or upon completion of Burton Shipyard Road, whichever is earlier, is considered as the “Road Improvement Period”. During the Road Improvement Period, Owner will ensure that two (2) lanes of traffic remain open for Contractors use of the portion of Burton Shipyard Road from Highway 27 to approximately 3040 feet east of Global Drive intersection to provide access to the Site according to the indicative standard in Exhibit 21-1. b) Convert Global Drive to private road from approximately twenty (20) feet south of the cemetery entrance to the Liquefaction Facility c) Convert Burton Shipyard Road to private road from, as a minimum, the location of the permanent plant gate house to east end at Calcasieu River bank [***] | At NTP Item a): 180 days after NTP; Item b): at NTP Item c): at NTP Item d): at NTP |
Description of Data/Information/Documents Provided | Date Provided or to be Provided | |
2.9 | Provide permanent electric power at the Benoit Switchyard tie-in points in accordance with the power supply requirements described in document the Scope of Facilities document 26089-200-G01-000-00001 with Exhibit E of Driftwood LNG Phase 1 Change Order number CO-002. | [***] weeks before first RFSU |
2.16 | Remove all existing Jefferson Davis substation above ground equipment, electrical lines and power poles along Global Drive and release servitude [***] days after NTP. After [***] days after NTP Contractor will remove the existing aboveground infrastructure at Owner’s expense. Note that Contractor will be removing switchyard concrete pad as part of its demolition work. | [***] Days after NTP |
2.26 | Owner to provide commissioning electric power at the Benoit Switchyard tie-in points in accordance with Exhibit D of Driftwood LNG Phase 1 Change Order number CO-002. Owner supplied power will be available at the four (4) Owner tie-in points (H frame structures) located at Benoit Substation East side fence in accordance with Exhibit E of Driftwood LNG Phase 1 Change Order number CO-002. | Contractor will provide 90-day notice of when CSU power will be required. Owner to supply a minimum of 15MW, 34.5kVac, 60Hz CSU power by the later of NTP + [***] months or 90-day notice from Contractor |
II. | Cost Adjustments |
Adjustment to Contract Price | ||
The original Contract Price was | USD 7,240,314,232 | EUR 375,344,119 |
Net change by previously authorized Change Orders (# CO-001) | USD 0 | EUR 0 |
The Contract Price prior to this Change Order was | USD 7,240,314,232 | EUR 375,344,119 |
The Contract Price will be (increased) (decreased) (unchanged) | ||
by this Change Order in the amount of | USD (18,958,942) | EUR 0 |
The new Contract Price including this Change Order will be | USD 7,221,355,290 | EUR 375,344,119 |
/s/ Howard Candelet | /s/ Andrey Polunin | |
Owner | Contractor | |
Howard Candelet | Andrey Polunin | |
Name | Name | |
SVP Projects, President Driftwood LNG | Senior Vice President | |
Title | Title | |
24th July 2019 | May 31, 2019 | |
Date of Signing | Date of Signing |